Singapore

Ease of Doing Business in

Singapore

This page summarizes Doing Business 2013 data for Singapore. The first table lists the overall "Ease of Doing Business" rank (out of 185 economies) and the rankings by each topic. It also lists the economy's distance to frontier (DTF)** measure. The rest of the tables summarize the key indicators for each topic and benchmark against regional and high-income economy (OECD) averages.

Economy Overview

Region East Asia & Pacific
Income Category High income
Population 5,183,700
GNI Per Capita (US$) 42,930
Doing Business 2013 Rank Doing Business 2012 Rank Change in Rank
1 1 0

Doing Business 2013 DTF** (% points) Doing Business 2012 DTF** (% points) Improvement in DTF** (% points)
91.7 91.7 0.0
Topic Rankings DB 2013 Rank DB 2012 Rank Change in Rank
Starting a Business 4 4 No change
Dealing with Construction Permits 2 2 No change
Getting Electricity 5 6 up 1
Registering Property 36 36 No change
Getting Credit 12 9 up -3
Protecting Investors 2 2 No change
Paying Taxes 5 4 up -1
Trading Across Borders 1 1 No change
Enforcing Contracts 12 13 up 1
Resolving Insolvency 2 2 No change

Economy Profile

1641.9 KB pdf file

Download Now

Getting Electricity

Info

The challenges required for a business to obtain a permanent electricity connection for a newly constructed warehouse are shown below. Included are the number of steps, time, and cost.

DB 2013 Rank 5 DB 2012 Rank 6 Change in Rank up1
DB 2013 DTF** (% points) 90.6 DB 2012 DTF** (% points) 90.6 Improvement in DTF** (% points) 0.0
Indicator Singapore East Asia & Pacific OECD

The number of procedures to obtain a permanent electricity connection. A procedure is defined as any interaction of the company employees or the company’s main electrician with external parties.

View methodology
Procedures (number)
4 5 5

The number of days to obtain a permanent electricity connection. The measure captures the median duration that the electricity utility and experts indicate is necessary in practice, rather than required by law, to complete a procedure.

View methodology
Time (days)
36 86 98

The cost is recorded as a percentage of the economy’s income per capita. Costs are recorded exclusive of value added tax.

View methodology
Cost (% of income per capita)
28.6 1,005.0 93.0
No. Procedure Time to Complete Associated Costs
1 The client’s Licensed Electrical Worker (LEW) submits application to SP Services Ltd and awaits quotation of connection fees 9 calendar days no charge
2 The client opens an electricity account, makes connection fee payment to SP Services Ltd and receives external works from SP PowerGrid Ltd 23 calendar days SGD 17,566.1
* 3 The appointed Licensed Electrical Worker (LEW) submits and obtains an electrical installation licence from the Energy Market Authority (EMA) on behalf of the customer 2 calendar days SGD 100.0
4 The appointed Licensed Electrical Worker (LEW) submits a turn-on appointment application to SP Services Ltd 4 calendar days no charge
* Takes place simultaneously with another procedure.

** The distance to frontier (DTF) measure shows the distance of each economy to the "frontier," which represents the highest performance observed on each of the indicators across all economies included in Doing Business since each indicator was included in Doing Business. An economy’s distance to frontier is indicated on a scale from 0 to 100, where 0 represents the lowest performance and 100 the frontier. Read more...