The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: SBD 5,200,000
  • City: Honiara

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Request and obtain approval from Town and Country Planning Board

BuildCo files an application for approval, with plans included, with the Town and Country Planning Board of the Planning and Building Department, which will review it for structure, environment, health, sewer, and fire regulations. The formula for the cost was updated in 2009 (0.5% of construction cost + SBD 250 (Planning Fee) + SBD 150 (Site Inspection)+ SBD 500( Excavation permit ) + SBD 200 ( Issue of permit )).

Agency: Town and Country Planning Board of the Planning and Building Department
31 days SBD 27,100
2 Request and receive Excavation Inspection



Agency: Town and Country Planning Board of the Planning and Building Department
1 day no charge
3 Receive and receive Foundation Inspection



Agency: Town and Country Planning Board of the Planning and Building Department
1 day no charge
4 Request water connection



Agency: Solomon Islands Electricity Authority (SIEA)
1 day no charge
* 5 Receive water inspection

Two days after the application is submitted, the Solomon Island Water Authority sends out an inspector.

Agency: Solomon Island Water Authority (SIWA)
1 day no charge
* 6 Connect to water



Agency: Solomon Island Water Authority (SIWA)
23 days SBD 1,600
* 7 Request telephone connection



Agency: Solomon Telekom Company Limited
1 day no charge
* 8 Receive telephone inspection

Two days after the application is submitted, the Solomon Island Water Authority sends out an inspector.

Agency: Solomon Telekom Company Limited
1 day no charge
* 9 Connect to fixed telephone line



Agency: Solomon Telekom Company Limited
9 days SBD 345