Dealing with Construction Permits
Info
Shown below are the procedures, time, and costs to build a warehouse, including obtaining necessary licenses and permits, completing required notifications and inspections, and obtaining utility connections.
| Indicator |
Shkodra, Albania |
Eastern Europe & Central Asia |
OECD |
The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. View methodology
Procedures (number)
|
21 |
19 |
14 |
The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. View methodology
Time (days)
|
176 |
226 |
143 |
Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. View methodology
Cost (% of income per capita)
|
382.7 |
486.7 |
78.7 |
| No. |
Procedure |
Time to Complete |
Associated Costs |
| 1 |
Request and obtain a recent property ownership certificate and a copy of the land plot map from the Immovable Property Registration Office (IPRO)
|
7 days
|
ALL 1,020 (ALL 400 for ownership certificate + ALL 400 for map + ALL 100 service fee + ALL 120 mailing fee)
|
| * 2 |
Request and obtain extract of master plan and general plan of the plot from the municipal Urban Planning Department
|
23 days
|
No cost
|
| * 3 |
Request and obtain document attesting that the firm has no unpaid taxes or fees from the municipal tax office
|
2 days
|
No cost
|
| * 4 |
Request and obtain opinion of the municipal Urban Planning Department
|
3 days
|
No cost
|
| * 5 |
Request and obtain updated information on the closest connection point to the water network from the local water authority (Ndërmarrja e Ujësjellësit dhe Kanalizimeve Sh.A. Shkodër)
|
3 days
|
No cost
|
| * 6 |
Request and obtain environmental approval from the Regional Agency of Environmental Protection (Agjencia Rajonale e Ruajtjes së Mjedisit—ARM)
|
3 days
|
ALL 2,000
|
| * 7 |
Request and obtain updated information on the closest connection point to the electricity grid from the electricity distributor (CEZ Shpërndarje Sh. A. Shkodër)
|
5 days
|
ALL 500
|
| * 8 |
Request and obtain Fire and Rescue Department approval (Policia e Mbrojtjes nga Zjarri dhe Shpëtimit - PMNZSH)
|
15 days
|
ALL 10,000
|
| 9 |
Request and obtain "buildable land" permit from the Technical Council of the municipal Urban Department (Këshilli Teknik) and the municipal Territorial Adjustment Council (TAC)
|
45 days
|
No cost
|
| 10 |
Apply and obtain building permit from the municipal Territorial Adjustment Council (TAC)
|
30 days
|
No cost
|
| * 11 |
Pay building permit fees at a commercial bank or post office
|
1 day
|
ALL 1,200,000 (3% of investment value)
|
| 12 |
Request inspection of property boundaries by licensed surveyor
|
1 day
|
ALL 3,000
|
| 13 |
Request inspection of construction foundations
|
1 day
|
ALL 3,000
|
| 14 |
Request on-site inspection of the completed construction skeleton
|
1 day
|
ALL 3,000
|
| 15 |
Request on-site inspection of the adjustment of the surroundings of the building according to the initial drawings
|
1 day
|
ALL 3,000
|
| * 16 |
Request connection and connect to electrical power grid (CEZ Shpërndarje sh.a. Shkodër)
|
25 days
|
ALL 40,000
|
| * 17 |
Request connection and connect to water and sewage services (Ndërmarrja e Ujësjellësit dhe Kanalizimeve Sh.A. Shkodër)
|
14 days
|
ALL 25,000
|
| * 18 |
Request connection and connect to telecommunications network (ALBtelecom)
|
10 days
|
ALL 4,800
|
| 19 |
Receive inspection and obtain compliance report
|
3 days
|
ALL 48,000 (0.12% of the investment value)
|
| 20 |
Request and obtain occupancy permit
|
30 days
|
ALL 5,000
|
| 21 |
Register property with the Immovable Property Registration Office (IPRO)
|
15 days
|
ALL 3,420 (ALL 3,000 registration fee + ALL 300 service fee + ALL 120 mailing fee)
|
* Takes place simultaneously with another procedure.