St. Kitts and Nevis

Dealing with Construction Permits in

St. Kitts and Nevis

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: XCD 2,800,000
  • City: Basseterre

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain Land Usage Approval (approval in principle)



Agency: Development Control and Planning Board
21 days no charge
2 Obtain Lot Plan



Agency: Development Control and Planning Board
7 days no charge
3 Obtain development permit (building permit)

According to the fee schedule for development permissions from the Development Control and Planning Board the cost is: ECD 20 for application fee + ECD 500 (for erection or extension to commercial, industrial, institutional and recreational structures -including warehouses- over 4,000 sq. ft) = ECD 520. Applications are turned down if documents for application are not complete (land usage approval and lot plan).

Agency: Development Control and Planning Board
35 days XCD 520
4 Receive Inspection from the Planning Department



Agency: Development Control and Planning Board
1 day no charge
5 Notify Planning Authority of the start of construction

Simple letter send to the Development Control and Planning Board will suffice

Agency: Development Control and Planning Board
1 day no charge
6 Receive Random Inspection

This is a random inspection. In most cases two inspections are conducted.

Agency: Development Control and Planning Board
1 day no charge
7 Receive Random Inspection

This is a random inspection. In most cases two inspections are conducted.

Agency: Development Control and Planning Board
1 day no charge
8 Receive final inspection



Agency: Development Control and Planning Board
1 day no charge
9 Obtain Occupancy Permit

Not given at the same time with final inspection. BuildCo must go to the Development Control and Planning Board to obtain it.

Agency: Development Control and Planning Board
1 day no charge
10 Obtain Water Connection

The Water Department is not involved in the approval. Because there is no sewage system in St. Kitts, septic tanks are used instead. A septic tank plan is submitted along with the rest of the application documents to the Local Planning Authority.

Agency: Electrical Department
35 days XCD 1,200
11 Obtain Fixed Telephone Line



Agency: Cable and Wireless
35 days XCD 150