St. Lucia

Dealing with Construction Permits in

St. Lucia

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: XCD 2,380,000
  • City: Castries

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain Health Department Approval

Site and floor plans are submitted that show adequate drainage and septic tanks.

Agency: Health Department
21 days XCD 250
2 Obtain Electricity Approval from Ministry of Communications and Works



Agency: Ministry of Communications and Works
14 days XCD 1,000
* 3 Obtain Approval from Fire Department



Agency: Fire Department
14 days XCD 600
4 Obtain Approval from DCA's commercial committee

The committee meets every 3 weeks. BuildCo must provide copies of all previous approvals. The Development Control Authority (DCA) does the approval process for public and commercial buildings in Saint Lucia.

Agency: DCA's Commercial Committee
42 days XCD 2,200
5 Receive inspection from WASCO (water department)



Agency: WASCO (water department)
17 days no charge
6 Obtain Water Connection



Agency: Ministry of Communications and Works
30 days XCD 150
* 7 Obtain Fixed Telephone Line



Agency: Cable and Wireless
10 days no charge
* Takes place simultaneously with another procedure.