Suriname

Dealing with Construction Permits in

Suriname

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: SRD 1,608,750
  • City: Paramaribo

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain a site map from a legally approved surveyor



Agency: Legally Approved Surveyor
2 days USD 250
2 Obtain building permit from Ministry of Public Works

The building's owner (BuildCo) must obtain a building permit at the Ministry of Public Works. This must be done before the start of construction.

The following documents must be submitted:
- The application form (a standard form).
- Architectural plans.
- Construction drawings and structural calculation.
- A site map made by a legally approved surveyor.
- The professional license of the building's owner (BuildCo).
The ministry will consult with the fire department and any other agency (a district commissioner, for example), if required.

Agency: Ministry of Public Works
180 days USD 260
3 Receive inspection by fire department



Agency: Fire Department
1 day no charge
4 Receive inspection by Ministry of Public Works



Agency: Ministry of Public Works
1 day no charge
5 Receive inspection by Ministry of Public Works



Agency: Ministry of Public Works
1 day no charge
6 Receive inspection by Ministry of Public Works



Agency: Ministry of Public Works
1 day no charge
7 Obtain approval from the Suriname Water Company (SWM) water supply company

Approval from the Suriname Water Company (SWM) can be obtained during construction and requires submissions of a plan of the water supply system. Installations can be done only by a firm approved by the SWM.

Agency: Electriciteits Bedrijf Suriname (EBS) power company
30 days SRD 56
8 Obtain water and sewage connection



Agency: Electriciteits Bedrijf Suriname (EBS) power company
180 days SRD 11,160
9 Receive inspection from SWM



Agency: Suriname Water Company (SWM)
30 days SRD 837
10 Obtain a fixed telephone line


14 days SRD 419
11 Obtain inspection certificate from fire department

By law, each construction project should be inspected by the Ministry of Public Works at least two to ten times. In reality, construction projects are never inspected. Other agencies, such as the fire department, power company, and water company, run one check to grant approval.

Agency: Fire Department
21 days no charge