Swaziland

Getting Electricity in

Swaziland

Below is a detailed summary of the procedures, time and cost required for a business to obtain an electricity connection for a newly constructed building in Swaziland.

This information was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 185 economies. The most recent round of data collection was completed in June 2012.

Compare Swaziland to 185 other economies.

  • Standardized Company

  • Name of Utility: Swaziland Electricity Board (SEC)
  • City: Mbabane
No. Procedure Time to Complete Associated Costs
1 Submit application at Swaziland electricity board (SEC) and await estimate

The customer has to submit the application for connection at the utility. Documents to submit are copy of the trading license, banking details, Copies of Director's ID, Lease Agreement/Property Ownership form
Agency: Swaziland Electricity Board (SEC)
30 calendar days SZL 20.0
* 2 Receive external inspection by the Swaziland electricity board

Representatives of the utility will conduct an external inspection of the site.
Agency: Swaziland Electricity Board (SEC)
1 calendar day no charge
3 Receive external connection works by utility

External connection works are carried out by the utility. The utility provides the transformer.
Agency: Swaziland Electricity Board (SEC)
99 calendar days SZL 277,615.0
* 4 Obtain approval for road crossing from City Council

If road crossing is involved, the client or his contractor has to get an approval from City Council.
Agency: City Council
1 calendar day no charge
5 Submit application for connection and pay meter

Once the connection works have been finalized the customer has to go again to the utility and bring his ID, he also has to show proof of physical residence . The customer pays the meter.
Agency: Swaziland Electricity Board (SEC)
1 calendar day SZL 6,678.3
6 Submit form to request internal wiring inspection, await meter installation, internal inspection and final connection by the utility

The electrician of the customer has to submit a form that the installation is ready for testing ( has to be submitted before the final inspection) - Form C (Certificate) - to request internal wiring inspection. The Utility would do this inspection at the end of the connection process. Representatives of the utility will come to the warehouse to install the meter and to conduct an internal inspection and to energize the connection.
Agency: Swaziland Electricity Board (SEC)
7 calendar days no charge
* Takes place simultaneously with another procedure.