Taiwan, China

Dealing with Construction Permits in

Taiwan, China

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: TWD 14,307,000
  • City: Taipei

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
* 1 Obtain proof of land title ownership from the city government



Agency: City Government
1 day TWD 50
2 Apply to the city government to define the building lines and check the boundary of land



Agency: City Government
16 days TWD 4,000
3 Obtain information about infrastructure from the water company



Agency: Taiwan Water Corporation
14 days no charge
* 4 Obtain information about electricity infrastructure from electricity provider



Agency: Taiwan Power Company (Taipower)
14 days no charge
* 5 Obtain information about telecommunications infrastructure from telecom company



Agency: Chunghwa Telecom Company Limited
14 days no charge
6 Obtain firefighting design approval from the fire protection authority



Agency: Fire Protection Authority
21 days no charge
* 7 Obtain waster water discharge permit from the industry park authority/ city government



Agency: City Government (Industry Park Authority)
7 days TWD 3,200
8 Apply for building permit from the city government

The building cost is assumed here to be TWD 15,200 per square meter for steel structures. Hence the building cost of the warehouse in this case is TWD 19,769,120. The cost of obtaining a building permit is 0.1% of the building cost estimated by the city government.

Agency: City Government
7 days TWD 19,769
9 Report the start date and present construction plan to the city government and pay the city government the air pollution protection fee before starting construction



Agency: City Government
1 day TWD 151,217
10 City government inspects layout of the building plan on the land site



Agency: City Government
1 day no charge
11 City government inspects at foundation stage



Agency: City Government
1 day no charge
12 City government inspects at second-floor stage



Agency: City Government
1 day no charge
13 City government inspects at roof construction stage



Agency: City Government
1 day no charge
14 Receive environmental inspection from the department of environmental protection (city government) at any time during construction



Agency: Department of Environmental Protection (City Government)
1 day no charge
15 Receive labor inspection from the department of labor (city government) at any time during construction

According to the Enforcement Rules of the Labor Safety and Health Law, BuildCo must assign at least one qualified staff member who holds a certificate of labor safety and hygiene training to the construction site for managing and supervising daily labor safety.

Agency: Department of Labor (City Government)
1 day no charge
16 Obtain firefighting inspection certificate from the fire protection authority



Agency: Fire Protection Authority
4 days no charge
* 17 Obtain address (house number) certification from the city government



Agency: City Government
3 days TWD 84
* 18 Obtain waste water connection certification from the environment protection bureau/ city government



Agency: City Government (Environment Protection Bureau)
10 days no charge
19 Obtain building usage (occupancy) permit from the city government

To obtain an occupancy permit, BuildCo requests that the city government approve the as-built drawings of the warehouse.

Agency: City Government
6 days TWD 100
20 Obtain building/ land ownership certificate from the city government.

The Department of Land in City Government issues a building/land ownership certificate on the basis of the building surface area calculation prepared by the architect and approved by the Department of Building Administration.

Agency: City Government (Department of Land)
18 days TWD 39,618
21 Apply for water supply from a local water company



Agency: Taiwan Water Corporation
1 day no charge
22 Receive inspection from water company



Agency: Taiwan Water Corporation
1 day no charge
23 Obtain connection to water

The whole process (from application to connection) may take 14–28 days.

Agency: Taiwan Water Corporation
19 days TWD 25,000
* 24 Request telephone line



Agency: Taiwan Power Company (Taipower)
1 day no charge
* 25 Obtain telephone line



Agency: Chunghwa Telecom Company Limited
3 days TWD 3,500
* Takes place simultaneously with another procedure.