Ease of Doing Business in

Ukraine

Ukraine Download Profile (1799.5KB, pdf)
Region Europe & Central Asia
Income Category Lower middle income
Population 45,198,200
GNI Per Capita (US$) 2,620
City covered Kiev

190

1

DB 2017 Rank

1

100

DB 2017 DTF (% points)

  • local_library
  • group
Topics DB 2017 Rank DB 2016 Rank info_outline Change in Rank DB 2017 DTF (% points) info_outline DB 2016 DTF (% points) info_outline Change in DTF (% points) info_outline
Overall 80 81 up
1
63.90 62.77 down
1.13
Starting a Business 20 24 up
4
94.40 93.88 up
0.52
Dealing with Construction Permits 140 137 down
3
61.42 61.36 up
0.06
Getting Electricity 130 140 up
10
58.45 54.84 up
3.61
Registering Property 63 62 down
1
69.61 69.44 up
0.17
Getting Credit 20 19 down
1
75.00 75.00
-
Protecting Minority Investors 70 101 up
31
56.67 50.00 up
6.67
Paying Taxes 84 83 down
1
72.72 72.99 down
0.27
Trading across Borders 115 110 down
5
64.26 65.15 down
0.89
Enforcing Contracts 81 93 up
12
58.96 57.11 up
1.85
Resolving Insolvency 150 148 down
2
27.50 27.92 down
0.42

Positive= Doing Business reform making it easier to do business.Negative= Change making it more difficult to do business.

DB 2017 Rank:

130

DB 2016 Rank:

140

Change in Rank:

up10

DB 2017 DTF (% points):

58.45

DB 2016 DTF (% points):

54.84

Change in DTF (% points):

up3.61

STANDARDIZED CONNECTION
Price of electricity (US cents per kWh) 9.1
Name of utility JSC Kievenergo
City Kiev
Indicator Ukraine Europe & Central Asia OECD high income
Procedures (number) info_outline 5 5.6 4.8
Time (days) info_outline 281 112.3 76.2
Cost (% of income per capita) info_outline 637.6 375.5 62.5
Reliability of supply and transparency of tariff index (0-8) info_outline 6 5.2 7.5
  • Measure of efficiency
    No. Procedure Time to Complete Associated Costs
    1

    Submit application to Kievenergo and await technical conditions

    Agency: Kievenergo

    The customer submits to Kievenergo an application for an electricity connection. Attached to the application the customer has to submit a number of documents: a letter with a company seal requesting the connection, bank details of the applicant, company statute, registration certificate from the tax authorities, registration certificate of the company, certificate stating that the company is included in the national company registry, document stating the appointment of the CEO, property ownership certificate and location plan of the property to be connected. After reviewing the application Kievenergo issues technical conditions. The technical conditions concern only the external connection. In general they may include instructions for construction of a new substation; lining of high-voltage and low-voltage cables; in a case of reconstruction works - participation of the subscriber in the given actions.


    The application for technical conditions is submitted to the Department of Development (департамент перспективного развития) at Kievenergo which is then internally passed on to the Regional Office in the particular area of Kiev where the warehouse is located and the regional office determines the point of connection. Technicians in the Regional offices know the network and the substations in their area very well and usually do not need to visit the site for preparation of technical conditions. At this point the connection contract is concluded which outlines the responsibilities between the customer and the utility.

    30 calendar days UAH 0
    2

    Await project design of external connection by private firm and its approval

    Agency: Project design firm

    Once the technical conditions are issued the customer hires a licensed project design company to prepare the electrical project design of the external connection. As part of the project design the company prepares a topogeodesic plan (топогеодезическую съемку М 1:500). The topogeodosic plan is prepared to determine the technical aspects of running cable through the landscape.

    While the project is being developed the approval of the location of the substation connection to the network and/or the route of the cable 10 kV and 0.4 kV has to be obtained from Kievenergo and from the Main Architectural Planning Organization. At this point the customer should have an operation permit for the warehouse or Main Plan with the Landscape Allocation Plan. The approvals are obtained by the project design firm.

    Considering the load (140 kW) when receiving an approval of the project of external connection from Kievenergo it is required to attach the project of the internal wiring of the warehouse which at this point should be approved as part of the general architectural design of the warehouse.


    While the project is being developed the approval of the location of the substation connection to the network and/or the route of the cable 10 kV and 0.4 kV has to be obtained from Kievenergo and from the Main Architectural Planning Organization. At this point the customer should have an operation permit for the warehouse or Main Plan with the Landscape Allocation Plan. The approvals are obtained by the project design firm.

    If a substation is required before the project design is submitted for approval to Kievenergo it will have to be approved at the State Energy Inspectorate (Energonadzor/“Dergenergonaglyadu”).

    Considering the load (140 kW) when receiving an approval of the project of external connection from Kievenergo it is required to attach the project of the internal wiring of the warehouse which at this point should be approved as part of the general architectural design of the warehouse.

    90 calendar days UAH 41,900
    3

    Await completion of external connection works

    Agency: Kievenergo

    Once the external connection design is ready and approved, the customer needs to make the payments for the connection.
    Kievenergo will select a contractor on a tender base who will under utility's supervision obtain the necessary permits and carry out the works.

    120 calendar days UAH 248,324
    4

    Conclude supply contract with Kievenergo (Energosbyt)

    Agency: Energosbyt (Kievenergo)

    Before turning on the power, the customer has to first conclude a supply contract with Kievenergo (Energosbyt). The supply contract can be concluded only after all the inspections are completed.

    The documents for the supply contract can be presented in the office or sent by mail. It is required to submit a number of documents regarding internal wiring including a Technical Report of the tests of the internal wiring which should be completed after the internal wiring was finished by an electrician.

    20 calendar days UAH 0
    5

    Request and receive turn-on of power by Kievenergo

    Agency: Kievenergo

    Once supply agreement is concluded, the customer can visit the dispatcher department of Kievenergo and request power turn on. The dispatcher department processes the order which permits it to turn off the 10 kV cable line, do the testing of the high voltage cable and finally turn on the electricity for the substation.

    21 calendar days UAH 0

  • Measure of quality
    Answer
    Reliability of supply and transparency of tariff index (0-8) 6.0
    Total duration and frequency of outages per customer a year (0-3) 2.0
    System average interruption duration index (SAIDI) 3.52
    System average interruption frequency index (SAIFI) 1.74
    Mechanisms for monitoring outages (0-1) 1.0
    Does the distribution utility use automated tools to monitor outages? Yes
    Mechanisms for restoring service (0-1) 1.0
    Does the distribution utility use automated tools to restore service? Yes
    Regulatory monitoring (0-1) 1.0
    Does a regulator—that is, an entity separate from the utility—monitor the utility’s performance on reliability of supply? Yes
    Financial deterrents aimed at limiting outages (0-1) 0.0
    Does the utility either pay compensation to customers or face fines by the regulator (or both) if outages exceed a certain cap? No
    Communication of tariffs and tariff changes (0-1) 1.0
    Are effective tariffs available online? Yes
    Link to the website, if available online http://kyivenergo.ua/ee-company/tarifi
    Are customers notified of a change in tariff ahead of the billing cycle? Yes
    Answer
    Price of electricity (US cents per kWh) 9.1

    Note:

    If the duration and frequency of outages is 100 or less, the economy is eligible to score on the Reliability of supply and transparency of tariff index.

    If the duration and frequency of outages is not available, or is over 100, the economy is not eligible to score on the index.