West Bank and Gaza

Dealing with Construction Permits in

West Bank and Gaza

Listed below is detailed summary of the procedures, time and costs to build a warehouse —including obtaining necessary licenses and permits, completing required notifications and inspections and obtaining utility connections. 

The information appearing on this page was collected as part of the Doing Business project, which measures and compares regulations relevant to the life cycle of a small- to medium-sized domestic business in 183 economies. The most recent round of data collection for the project was completed in June 2011.

  • Building a warehouse

  • Estimated Warehouse Value: ILS 1,648,511
  • City: Ramallah

About This Topic

To see indicator data for all economies, see the Dealing with Construction Permits page. To see how economies rank, see the Rankings page.

No. Procedure Time to Complete Associated Costs
1 Obtain location map from municipality

BuildCo must obtain a location map form the municipality to check that the proposed constructions project is allowed on this land.

Agency: Municipality
7 days ILS 72
2 Obtain survey map from a licensed surveyor

The survey map is usually at a scale of 1:500 or 1:250 and shows, in addition to the boundaries, the levels and/ or contour lines, the site, and the surroundings, including sewerage, electricity, telephone, and water connections.
10 days USD 1,200
3 Make soil test

A law requiring a soil exam went into effect in 2001, but because of the economic situation, some companies do not comply with it. However, since January 2005, the Engineers Syndicate stopped approving any plan without the soil test for projects exceeding 200 sq. m. A minimum of 3 boreholes must be made on the proposed site. If the building is an extension above an existing building, a report about the state of the existing building must be submitted.
14 days ILS 9,592
4 Hire independent syndicate engineer to review building plans and approve them for submission

As required by the Engineers’ Syndicate, BuildCo must hire an outside engineer to submit the plans. Each project has to be licensed by a locally registered and licensed engineering/ architecture office even if the project has in house engineers and architects. Drawings are checked in Ramallah, but a jury from outside the city will check the plans. The cost includes the Engineers Syndicate fees.

Agency: Independent Syndicate Engineer
21 days USD 5,202
5 Obtain building permit from the municipality

To obtain a building permit from the municipality, BuildCo must submit the following documents in five copies, one copy each for the consulting office, the municipality, the Ministry of Tourism and Antiquities, and the engineer, as well as one copy that will be returned to BuildCo: - Land property title, including, site map, location map, city-land parcel number, and area regulations signed by a surveyor. - Documents about dimensions. - Project drawings: the proposed site plan and architectural plans, including dimensions, furniture, and reflected ceiling; and elevation, sections, and area diagrams with door and window schedules. - Structural drawings, including foundation plans, slabs, and details. - Plans for utilities, lighting, and earthling diagrams. - Mechanical plans for hot and cold water supplies, heating/cooling, ventilation, and sewerage. - Soil test. - Application form. The municipality must approve all copies mentioned above. The Ministry of Tourism and Antiquities must also approve BuildCo’s set of copies, as do the utility companies.

Agency: Municipality
21 days USD 5,202
* 6 Obtain no objection letter from the Electricity Company regarding the connection to utilities



Agency: Electricity Company
1 day no charge
* 7 Obtain no objection letter from the Water Company regarding the connection to utilities



Agency: Water and Sewage Company (GEKA)
1 day no charge
* 8 Obtain civil defense permit

To obtain a civil defense permit, BuildCo must submit the following documents: - Land property title. - Documents about dimensions. - Project drawings. - Certificate of professional engineer - Project acceptance from the Engineers Syndicate. - Application form.

Agency: Civil Defense
14 days no charge
9 Obtain excavation permit



Agency: Municipality
31 days no charge
10 Receive foundation inspection

During construction the municipality randomly inspects the excavation work.

Agency: Municipality
1 day no charge
11 Submit concrete casting permit to Engineers syndicate for stamping



Agency: Engineers syndicate
1 day no charge
12 Submit stamped concrete casting permit to the Municipality



Agency: Municipality
1 day no charge
13 Request and receive final inspection



Agency: Municipality
1 day USD 8
14 Bring municipal letters of approval to water and sewage company (GEKA) and make appointment for inspection



Agency: Water and Sewage Company (GEKA)
1 day no charge
15 Bring municipal letters of approval to the phone company to obtain fixed telephone line



Agency: Electricity Company
1 day no charge
16 Receive water and sewage inspection

The time from scheduling an appointment to when the inspector installs the meter is a week.

Agency: Water and Sewage Company (GEKA)
1 day no charge
* 17 Obtain water and sewage connection

The time and cost of obtaining an electricity connection depend on how much power is needed. In this case, only a 100-ampere connection is needed. If more than 1,000 amperes are need, a transformer is necessary, which costs a few thousand U.S. dollars and takes a month.

Agency: Electricity Company
3 days ILS 3,500
* 18 Receive inspection and obtain phone connection



Agency: Telephone Company
7 days ILS 600
* Takes place simultaneously with another procedure.