The total number of procedures required to build a warehouse. A procedure is any interaction of the company’s employees or managers with external parties. More informationProcedures (number) | The total number of days required to build a warehouse. The measure captures the median duration that local experts indicate is necessary to complete a procedure in practice. More informationTime (days) ▲ | Cost is recorded as a percentage of the economy’s income per capita. Only official costs are recorded. More informationCost (% of income per capita) |
||
|---|---|---|---|---|
| Popayán | 1 | 11 | 38 | 85.5 |
| Santa Marta | 3 | 13 | 43 | 125.5 |
| Riohacha | 6 | 14 | 48 | 106.1 |
| Bogotá | 7 | 11 | 74 | 402.8 |
| Montería | 5 | 13 | 75 | 116.2 |
| Sincelejo | 8 | 14 | 85 | 141.5 |
| Tunja | 3 | 13 | 86 | 104.9 |
| Valledupar | 2 | 13 | 89 | 79.7 |
| Barranquilla | 8 | 13 | 91 | 186.9 |
| Cúcuta | 18 | 16 | 96 | 208.1 |
| Manizales | 10 | 13 | 98 | 209.6 |
| Cartagena | 16 | 14 | 107 | 293.7 |
| Pereira | 14 | 14 | 121 | 171.6 |
| Armenia | 13 | 14 | 123 | 122.0 |
| Neiva | 10 | 14 | 127 | 112.8 |
| Pasto | 10 | 13 | 140 | 147.2 |
| Cali | 20 | 19 | 146 | 175.1 |
| Villavicencio | 21 | 16 | 151 | 269.0 |
| Bucaramanga | 19 | 18 | 160 | 126.8 |
| Medellín | 15 | 13 | 181 | 231.3 |
| Ibagué | 16 | 14 | 217 | 144.8 |